The party wall guide for homeowners

When the Party Wall Act applies to your extension or loft, what notice you need to give, and how the process works.

The party wall guide for homeownersGuide

What the Act covers

The Party Wall etc. Act 1996 applies when you work on a wall shared with a neighbour, build on the boundary line, or dig foundations close to a neighbour's building. The government's party walls guidance sets out the detail.

Giving notice

You need to give your neighbours written notice before work starts. For work on a party wall the notice period is two months, and for excavations near their foundations it is one month.

If your neighbour agrees

If your neighbour consents in writing, work can go ahead once the notice period ends. It is still sensible to record the condition of their property first.

If they do not agree

If they dissent, a party wall surveyor, or one for each side, prepares an award setting out how the work will be done. We recommend experienced party wall surveyors.

How we help

We tell you at the consultation whether the Act is likely to apply and plan it into the programme so it does not hold up the build.

Questions

Quick answers.

Often, yes, because loft steels are usually set into the party wall on semi-detached and terraced houses.

Usually the person doing the work pays the reasonable costs of both surveyors.

They cannot stop work that follows the Act, but they can ask for an award setting out how it is done.

Free consultation

Get a free consultation.

Tell us about the project and we'll call you back to book a free visit. Fixed-price quote, no obligation.

What's the project?
When would you like to start?
Your details

Free and no obligation. Your details only go to the Surrey Building team.

Thanks.

We'll call you within one working day to book your free consultation.

Office01483 355025 Mobile07599 657303
Office address1 Epsom Road, Guildford GU1 3JT